Modular Fabrication Continues on PureCycle’s Ultra-Pure Recycled Polypropylene Process Plant– Project Update #3

Modular Fabrication Continues on PureCycle’s Ultra-Pure Recycled Polypropylene Process Plant– Project Update #3

Module assembly continues to advance on PureCycle Technologies first-of-a-kind ultra-pure recycled (UPR) Plant. Since our last update, pipe racks for four modules are nearing completion with pipe insulation now being installed. Two other process modules have equipment installed and instrument and electrical installation is underway followed by steam control trace and piping insulation. The remaining modules are being prepped for steel erection with equipment is arriving on-site regularly to be installed into module steel structures. Module piping fabrication and installation are ramping up quickly as steel structures are readied for the continuation of module assembly. We are excited to see all the progress being made as this project comes to life.